I promised to keep you up to date so here goes:
As mentioned before, our contractors James Breck Ltd have subcontracted the scaffolding build to specialists ASC Ltd Scaffolding. Although the start date had been agreed in writing as being 17th March 2014, ASC apparently had some issues that caused an initial delay which was not immediately communicated to our Contracts Manager Peter McKeowan (who was on paternity leave at the time - congratulations on his new arrival).
A revised start date of Wednesday 26th March was agreed on his return, as communicated here, but again ASC had some issues that meant they arrived on Thursday 27th instead, when the basement and ground floor layers of the scaffold were erected.
![]() |
Scaffold as at Friday 28 March 2014 |
Peter called me this morning with all this information, to apologise for the delays, and to confirm that ASC will be back tomorrow, Tuesday 1 April 2014, to continue the build.
A revised project schedule will be provided soon, and I'll share it here.
Thanks.
Catriona
PS As a bonus, here's a wee mini scaffold my friends made for me when I told them we were underway - bless them, they know how big a deal this is! The boat-cake in the middle represents me sailing away from it all...