| Yellow cabin being removed from front of the building on Friday 25 July 2014 |
Next meeting yet to be confirmed, but likely to be mid/late September.
Thanks,
BSORA Committee
The purpose of this 'blog' is to enable open and regular communication between owners and tenants regarding the maintenance and repair of our property.
![]() |
| Yellow cabin being removed from front of the building on Friday 25 July 2014 |
![]() |
| Remaining Scaffolding on Montgomery Street Elevation as at 20 July 2014 - various new stones visible to right of image |
![]() |
| Chimney G, partially rebuilt, viewed from Brunswick Street side 17 June 2014 |
![]() |
| Chimney G, rebuilt but not yet rendered, viewed from Brunswick Street side 28 June 2014 |
![]() |
| Chimney G, rebuilt but not yet rendered, viewed from Montgomery Street side 28 June 2014 |
![]() |
| Chimney G as at 21 May 2014 - Now you see it.... |
![]() |
| ..and now you don't....Chimney G, gone, as at 11 June 2014 |
![]() |
| Chimney G this morning 18 June 2014, both old and new, side by side on Montgomery Street. |
![]() |
| Zoomed in to see the new rebuilt Chimney H at the rear 3 June 2014 |
![]() |
| Removed stonework visible to the right of the double window at 3F2. 3 June 2014 |
![]() |
| New stonework now visible to right of double window at 3F2 and also between the panes at 2F2 below. 6 June 2014 |
![]() |
| Vertical stone piece to edge of window at 3F2 removed - visible lying on the scaffold. 5 June 2014 |
![]() |
Vertical stone piece at 3F2 window
now replaced.
6 June 2014
|
![]() | ||
| Removed stonework from 3F2 - new stones lying on scaffold 1 June 2014 |
![]() |
| Stones removed by living room window of 3F2 - new stone on scaffold 1 June 2014 |
![]() |
| New stone in place to right of double window at 3F2.6 June 2014 |
![]() |
| Chimney G stone deterioration May 2014 (1) |
![]() |
| Chimney G stone deterioration May 2014 (2) |
![]() |
| Chimney G stone deterioration May 2014 (3) |