I'll be honest: it was with some relief that I saw ASC were here this morning, as I set off in the pouring rain, and it wasn't even an April Fool - we do actually have another (bit of a) layer in place!
![]() |
Scaffolding as at Tuesday evening 1 April 2014 |
Meanwhile, I got this message from David Burrup today :
Regarding the delays so far, James Breck Ltd have passed on the following to you;
‘Apologies for the delay to date, certainly not the start we would hope for or expect. Our scaffolding contractor has had some difficulties with resources over the past few weeks, these issues have now been addressed. Moving forward the scaffolders are back on site today as planned and we expect the elevation scaffolding to be complete with handover certs for Friday of this week.’
So, as agreed a revised programme reflecting the delayed start has now been provided:
Revised Programme 1-1-14.
Also forwarded was the letter you should each get a copy of through your doors this week advising about access on Saturday.
Chimney Initial Visit
(Both documents will also be accessible via Relevant Documents and Links page).
I hope this helps you feel informed of progress, especially for those not currently resident.
Catriona