Dear all,
Despite appearances,
things are moving very quickly and it's not easy to keep up to date, far less keeping everyone in the loop. Nevertheless,
here is an attempt to do so:
As explained
previously, because the orginal survey was carried out in Nov 2011,
it was no surprise that there might be some variations to the
original estimate.
These were discussed
at the Meeting held on 27 April 2014, where a majority decision was
taken to accept the following proposals. (Minutes to follow)
The variations agreed so far are:
Since then, though, we
have received some further variations, this time to the rear
elevation. These are illustrated in the document you can find here.
They include clearing the greenery out of the downpipes, and replacing
an additional badly decayed lintel, shown below. These are, inevitably, further additional costs. There is a further lintel which we could replace, if we choose to, although at this stage as it is not deemed essential, the proposal is to leave it in order to curb costs as far as possible.
 |
Lintel to2f1- No allowance in tender, cement repair failing and stonework underneath is
in poor condition |
 |
Greenery growing in downpipes |
Taken altogether the overall increase to
the project costs at this stage are likely to be approximately an extra £5,200 plus VAT. This represents just under 10% on the originally estimated costs, equivalent to a sum in the region of about £500 per flat (inc. VAT), although the
detailed apportionments by property have yet to be confirmed. I do appreciate that this is not an insignificant sum, but in the scheme of things (and certainly in the old stat notice days) could probably have been worse.
We will aim to get firmer figures as soon as possible. If you have any questions, please contact either bsora@hotmail.co.uk or David Burrup at DM Hall and we will do our best to answer as best we can.
In the meantime, DM
Hall have provided the following update for Week 3
Lead works complete to EF
Lead works in progress to CD
Lead works in progress to B
Cast iron redecorations in
progress
Cupola overhaul in progress
Chimney rebuild to H instructed
29/4/14
Re-rendering to G&H to be
completed once rebuild to H complete
Masons expected on site WC
12/5/14 to begin chimney rebuild
In
terms of stonework to elevations, there is a lead in time of up to 6
weeks for stonework. If additional stone units are to be
instructed this needs to be confirmed to James Breck before 9/6/14 to
avoid additional scaffold hires. The additional charges would
be as per the rates previously confirmed.
As ever, every reasonable attempt will be made to keep you informed of what is happening, and what this is likely to mean to us all.
Thanks,
Catriona
for
BSORA