Monday, 19 May 2014

Update as at 19 May 2014

Update from David on Friday afternoon:


Quick update for week 4 as follows:
  • A few days have been lost due to the poor weather, (?)  hopefully this can be made up without effecting the program.
  • Lead work to chimneys E+F completed (see attached) (as reported last week)
  • Lead work to chimneys C+D in progress ( as reported last week)
  • Cupola haffits complete (see attached)
  • Cast iron decorations complete to front elevation
  • Chimney works to begin on Monday. 
(Photos and more info to follow - there is some fault with Blogger that won't let me post so will just get this basic update out).

Regards, 

Catriona
for
BSORA

(See update below, now that Blogger working again 20th May)

Leadwork to Chimney E and F
Cupola Haffits done, whatever they are

Please note that the following additional works have already been agreed and instructed: 
  • Rebuild Chimney H
  • Patch to - render to chimney C
  • Apron flashings to chimneys C,D,E,F
  • 3nr moulded string course cills top level
  • Moulded cill 1f3 2nr
  • Blocking course projected string detail 
  • Replace jamb full height (originally included for indenting)
As mentioned in the post from 7 May 2014, these variations were agreed at the meeting on 27 April 2014.  To avoid incurring additional scaffolding costs, we have since been under some pressure to make fairly quick decisions regarding the variations to the rear elevation, and so it was finally agreed to proceed with the following: 
  • Rear 2nd floor lintel 
  • Rear downpipe cleared/joints repaired 

If you have any questions, please contact either bsora@hotmail.co.uk or David Burrup at DM Hall and we will do our best to answer as best we can.

Thanks,

Catriona
for
BSORA

No comments:

Post a Comment